Innovative Process Flow Sheet Selected with High Recoveries
Released
Released
Announcement PDF
ASX Announcement
1 October 2025
ASX: OD6
INNOVATIVE PROCESS FLOWSHEET SELECTED WITH HIGH
RECOVERIES AT THE SPLINTER ROCK RARE EARTH PROJECT
ANSTO Metallurgical Testwork program and CPC Engineering Optioneering Study
recommends preferred process flowsheet for the Splinter Rock Rare Earth Project.
– JORC Mineral Resource of 682Mt @ 1,338ppm TREO
Highlights:
•
Optioneering Study recommends preferred process flowsheet moving forward for Splinter
Rock’s clay-hosted rare earth mineralisation as study wraps up
•
Innovative Process Flowsheet Incorporates
o Heap Leach with Nanofiltration (NF), Ion Exchange (IX) and Impurity Removal (IR)
o ~75% Nd & Pr overall Recovery
o High-quality Mixed Rare Earth Carbonate (MREC) of ~56% TREO
o High-quality Mixed Rare Earth Hydroxide (MREH) of ~59% TREO
o Superior product quality with low levels of impurities (Al, Fe, P, Si)
o Extremely low uranium and thorium content (<0.001% U + Th)
o Optimised capital and operating cost drivers
•
Metallurgical Diamond Core Drill Campaign Nearing Completion: Set to deliver 2 to 2.5
tonnes of rare earth bearing core to ANSTO later in October.
•
ANSTO to Commence Advanced Optimisation and Scale-up Tests this quarter: with results
due progressively during the first half of 2026.
•
Mining Study to Commence to consider pit shell analysis, stripping ratios, high level mine
scheduling and preliminary mining costs
Managing Director Brett Hazelden, commented:
“The selection of a preferred flowsheet marks a major milestone for Splinter Rock. This outcome provides confidenc e
in our ability to produce a high-value, low-impurity MREC or MREH product that is highly attractive to global supply
chains. With this stage complete, we now move into large-scale testwork at ANSTO and commence mining studies
at the Inside Centre Deposit.
Importantly, discussions with potential offtake partners, separation facilities, end-users and governments continue
to reinforce the strategic value of Splinter Rock..”
MagREE (Magnet Rare Earths) = Nd + Pr + Tb + Dy)
MagREO (Magnet Rare Earth Oxide) = Nd 2O3 + Pr6O11 + Tb 4O7 + Dy2O3
TREO (Total Rare Earth Oxide) = La 2O3 + CeO2 + Pr6O11 + Nd 2O3 + Sm2O3 + Eu 2O3 + Gd 2O3 + Tb 4O7 + Dy2O3 + Ho 2O3 + Er2O3 + Tm2O3 + Yb 2O3 + Lu 2O3 + Y2O3.
OD6 Metals Limited (OD6 or the Company) is pleased to announce that the CPC Optioneering
Study, supported by metallurgical testwork completed by the Australian Nuclear Science and
Technology Organisation (ANSTO), has delivered a preferred process flowsheet for the Splinter
Rock Rare Earth Project. This innovative flowsheet achieves high recoveries, superior product
quality, and improved cost outcomes, positioning Splinter Rock as one of the leading clayhosted rare earth developments in Australia.
This work brings a close to the Optioneering Study and enables work to commence on the next
phase of advanced Scaleup Metallurgical Testing and Project Studies.
What have been the Aims for Flowsheet Development?
The Optioneering Study and testwork program has taken the opportunity to not only test a standard
flowsheet but to look at enhancements that can make the Splinter Rock Rare Earth project more
resilient. As a result of having multiple technically viable flowsheets, OD6, ANSTO and CPC
Engineering (CPC) have started with the end product in mind first with the key aims including:
•
Produce a High Quality Mixed Rare Earth Carbonate (MREC) or Mixed Rare Earth Hydroxide (MREH)
•
Enable the final product to be sold to multiple different countries and downstream process worldwide
•
Balance a simple process with the need to produce a quality product
•
Optimise product payability as a percentage of Rare Earth Oxide (REO) pricing
•
Review benefits of removing Uranium and Thorium from the final product to enable safe transport
•
Optimise Overall Recovery from mine through to the final product
•
Minimise Acid and other reagent consumptions
•
Lower energy consumption
•
Optimise capital and operating costs
•
Optimise Project economics
•
Allow for Expandability
•
Consider technical and commercial rick
Preferred Process Flowsheet Plus Metallurgical and Study Outcomes to Date
OD6, CPC and ANSTO have successfully demonstrated and recommended a multi-stage processing pathway
outlined in Figue1 (refer Flowsheet 6 below), that efficiently produces a superior quality product with low
impurities, that has achieved high REE element total flowsheet recoveries as detailed in Figure 2.
The Preferred Process flowsheet has built on the metallurgical and optioneering study outcomes to date which
have been progressively reported to the ASX as per the following:
1.
Heap Leaching – Simple, low-acid usage leaching of rare earth-bearing clays to generate enriched
leachate solution (refer ASX 16 October 2024)
2.
Nanofiltration (NF) – Recycling of Acid, concentration of REEs and reduction of liquid volume
produced downstream (refer ASX 4 August 2025)
2
3.
Ion Exchange (IX) – Concentration of rare earth elements and enhanced removal of iron (Fe) and
aluminium (Al) reducing downstream processing risk (refer ASX 7 August 2025)
4.
Impurity Removal (IR) – Final removal of residual deleterious elements (e.g. Al, Ca, Fe, U, Th, P) to meet
high product quality and low impurity specifications.
5.
Product Precipitation – Recovery of high-grade Mixed Rare Earth Carbonate (MREC) or Mixed Rare
Earth Hydroxide (MREH) from purified solution (refer ASX 13 August 2025)
6.
Chlor-Alkali Facility (CAF) – Confirmed as a cost-reduction measure, producing key reagents onsite
and materially lowering operating costs (refer ASX 2 September 2025)
7.
Low Cost Route – The Optioneering Study supports heap leaching as the lower cost and higher
recovery option when compared to conventional agitated tank leaching for the Splinter Rock Rare Earth
Project at the Inside Centre Deposit (refer ASX 11 September 2025)
The final MREC/MREH products contain elevated concentrations of Nd, Pr, Dy and Tb, collectively representing
a high-value magnetic rare earth mix highly sought after in permanent magnet supply chains. Benchmark
payability for MREC and MREH typically ranges between 70–85% of REO basket value.
The Company aims to be a 6,000 plus tonnes per annum (tpa) producer of REO , in either the form of Mixed
Rare Earth Carbonate (MREC) or Mixed Rare Earth Hydroxide (MREH) in 5 years (refer ASX 11 September 2025)
Figure 1: Preferred Process Flowsheet from ANSTO Testwork and CPC Optioneering Study
3
Inside Centre Deposit Extraction by REE
Total REE % Recovery
80
70
60
50
40
30
20
10
0
La
Ce
Pr
Nd
Sm
Eu
Gd
Tb
Dy
Ho
Er
Tm
Yb
Lu
Y
TREY
Figure 2: Anticipated Inside Centre Total REE Recovery by Element Utilising the Preferred Process Flow Sheet
Flowsheets Tested and Considered
OD6 has sequentially tested several flowsheets over time starting with a relatively simple flowsheet that would
produce a lower quality product, through to a more complex flowsheet with a higher quality product, higher
recovery of REEs plus lower reagent usage requirements.
Each flowsheet tested is summarised below with its pros and cons.
Flowsheet 1
Simpletest flowsheet where by the ore is heap leached, followed by a standard two stage Impurity Removal (IR)
at a pH of ~4.15 and ~5.5, followed by precipitation of a MREC or MREH at a pH ~7.5.
Pros and Cons:
•
Simple process
•
Overall REE Recovery is lower due to REE losses in the Impurity Removal stage
•
No acid recovery and recyling
•
IR circuit required to treat 100% of the volume of heap leach liquor
•
Average product quality due to higher Al, Fe, U and Th residual impurities
4
Flowsheet 2
Builds on Flowsheet 1 with the introduction of a REE Ion Exchange (IX) module prior to Impurty Removal. The IX
concentrates the REEs onto a Resin that is then eluted back into solution prior to the IR circuit (similar to how
carbon is utilised in a gold CIP/CIL circuit). The volume of liquor reporting to the IR circuit is signifcantly
decreased. IR is a standard two stage impurity removal at a pH of ~4.1 and ~5.5, followed by precipitation of a
MREC or MREH at a pH ~7.5.
Pros and Cons:
•
IX Concentrates REEs requireing a smaller IR circuit
•
Some impurity rejection during IX
•
IX barren liquid unable to be recycled
•
Overall REE Recovery is similar to Flowsheet 1
•
No acid recovery and recyling
•
IR circuit treats a reduced volume of heap leach liquor
•
Average product quality due to higher Al, Fe, U and Th residual impurities
Flowsheet 3
Builds on Flowsheet 2 with the introduction of a Nanofiltration (NF) to recover acid from the IX barren liquid.
Recovered acid is then recycled to the Heap leach circuit. The IX concentrates the REEs on to a Resin that is then
eluted back into solution prior to the IR circuit. IR is a standard two stage impurity removal at a pH of ~4.1 and
~5.5, followed by precipitation of a MREC or MREH at a pH ~7.5.
Pros and Cons:
•
>80% acid recovery in the NF permeate
•
IX Concentrates REEs requireing a smaller IR circuit
•
Some impurity rejection during IX reducing RE loss in IR
•
Overall REE Recovery is improved marginally
•
IR circuit treats a reduced volume of heap leach liquor
•
Circuit complexity increasd in number of steps
•
Extra NF circuit increase Capital Cost but loweres operating cost due to reduced acid requirements
•
Average product quality due to higher Al, Fe, U and Th residual impurities
5
Flowsheet 4
Builds on Flowsheet 1 with the introduction of a Nanofiltration (NF) to recover acid direct from the Heap Leach
and then recycled to the Heap leach circuit. NF reduces liquor volume reporting the the IR circuit signifantly. IR
is a standard two stage impurity removal at a pH of ~4.1 and ~5.5, followed by precipitation of a MREC or MREH
at a pH ~7.5.
Pros and Cons:
•
>80% acid recovery in the NF permeate
•
No Impurity rejection during NF
•
NF Concentrates REEs requireing a smaller IR circuit
•
Overall REE Recovery is similar to Flowsheet 1
•
IR circuit treats a reduced volume of heap leach liquor
•
Removes cost of IX circuit
•
Average product quality due to higher Al, Fe, U and Th residual impurities
Flowsheet 5
Builds on Flowsheet 4 and Is a reordering of Flowsheet 3. Nanofiltration (NF) recovers and recycles acid to the
Heap leach circuit. NF reduces liquor volume reporting to the IX circuit signifantly. The IX concentrates the REEs
on to a Resin that is then eluted back into solution prior to the IR circuit. The volume of liquor reporting to the
IR circuit is reduced further and impurities also reduced. IR is a standard two stage impurity removal but given
the improved feed volume and quality the pH set points can be optimsed to ~3.5 and 4.4, followed by
precipitation of a MREC or MREH at a pH ~7.1 to 7.5.
Pros and Cons:
•
>80% acid recovery in the NF permeate
•
NF reduces liquor volume to IX by ~65% decreasing cuircuit size
•
IX Concentrates REEs requireing a smaller IR circuit
•
Cleaner IX eluate allows for simple IR and lower pH, reducing REE loss due to coprecipitation
•
Overall Recovery REE is improved
•
IR circuit treats a further reduced volume of heap leach liquor
•
Circuit complexity increasd in number of steps but total plant size and equipement requirements
signifantly decreased
•
Total Capital Cost lower due to smaler downstream circuit sizes and also lowers operating cost due to
reduced acid requirements and plant size
•
Improved product quality due to better impurity removal of Al and Fe, but not, U and Th
6
Flowsheet 6
Builds on Flowsheet 5. An an additional U/Th Ion Exchange step is added to improved product quality and
increase payability. No change to NF, REE IX and IR operating circuits.
Pros and Cons:
•
>80% acid recovery in the NF permeate
•
NF reduces liquor volume to IX by ~65% decreasing cuircuit size
•
IX Concentrates REEs requireing a smaller IR circuit
•
Cleaner IX eluate allows for simple IR and lower pH, reducing RE loss due to coprecipitation
•
Overall Recovery REE is improved
•
IR circuit treats a reduced volume of heap leach liquor
•
Circuit complexity increasd in number of steps but total plant size and equipement requirements
signifantly decreased
•
Total Capital Cost lower due to smaler downstream circuit sizes and also lowers operating cost due to
reduced acid requirements and plant size
•
Improved product quality due to better impurity removal or Al, Fe, U and Th
Next Steps
Complete Metallurgical Core Program: Drilling due to be completed in October with core samples dispatched
to ANSTO also in October.
ANSTO Testwork Scale Up: Heap Leach and Impurity Removal testwork as described above
•
Heap leach Optimisation: Heap Leach duration and kinetics, Acid strength and consumption, Counter
current heap configuration, Particle agglomeration methodology
•
Impurity Removal Verification: Nanofiltration (NF) acid recovery, Ion Exchange (IX) selectivity and
elution to reduce Fe/Al and trace U/Th, plus two stage Impurity removal (IR) optimisation
•
Bulk MREC and MREH Production: Precipitation to produce >1 kg of MREC and/or MREH for
customer qualification, offtake discussions, and to assess commercial payability options
Mining Study to Commence: Burnt Shirt have been engaged to conduct a mine options study at the Inside
Centre Deposit to consider geology, mining method, pit shell analysis, stripping ratios, high level mine
scheduling and preliminary mining costs
Engagement with potential offtake partners: To assess commercial payability options for MREC and MREH
products.
Engagement with government and potential financing partners: OD6 has and continues to engage
government and potential financing organisations. This is anticipated to be a continuous process over the
development cycle.
Selective Nd, Pr, Tb and Dy Oxide Production Potential: Whilst initial development at Splinter Rock targets
MREC or MREH, the onsite Chlor-Alkaly Facility (CAF) positions OD6 for potential future production of individual
oxides (Nd, Pr, Dy, Tb, and potentially Sm, Y) through a chloride-based SX process. Discussions with ANSTO to
conduct a desk top assessment are advancing and may be commenced during 2025.
7
Competent Persons Statement
The scientific and technical information that relates to process metallurgy is based on information reviewed by Mr Brett Haze lden
(Managing Director and CEO) of OD6 Metals Limited. Mr Hazelden is a Member of the AusIMM and has sufficient experience
relevant to hydrometallurgical processes to qualify as a Competent Person as defined by the JORC Code. Mr Hazelden owns shares
in the Company and participates in the Company’s employee securities incentive plan. Mr Hazelden consents to the inclusion in this
announcement of the matters based on their information in the form and context in which it appears.
Information in this report relating to Mineral Resource estimation and Exploration Results is based on information reviewed b y Mr
Jeremy Peters who is a Fellow of the Australasian Institute of Mining and Metallurgy and a Chartered Professional Geologist a nd
Mining Engineer of that organisation. Mr Peters is a Director of Burnt Shirt Pty Ltd, consulting to OD6 and has sufficient ex perience
which is relevant to clay-hosted rare earth mineralisation to qualify as a Competent Person as defined by the 2012 Editi on of the
Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Peters consents to the inclusi on of
the data in the form and context in which it appears.
Aspirational Production Target Cautionary Statement
The Company cautions that the above aspirational statement of prospective production and the aspirational production target
ranges adopted in the optioneering study (refer ASX 11 September 2025) are conceptual in nature and the target ranges were
adopted solely to support comparative techno -economic assessment within the optioneering study. They are not production targets
or forecast financial information derived from production targets for the purposes of the Corporations Act or ASX Listing Rules and
there is a low level of geological confidence associated with any potential production parameters at this stage. Further expl oration,
engineering, and feasibility work are required before OD6 can dete rmine the likelihood of establishing Ore Reserves and/or
production targets or before making any final investment decision. There is no certainty that the conceptual ranges adopted w ithin
the optioneering study will be realised.
Forward Looking Statements
Certain information in this document refers to the intentions of OD6 Metals, however these are not intended to be forecasts,
forward looking statements, or statements about the future matters for the purposes of the Corporations Act or any other appl icable
law. Statements regarding plans with respect to OD6 Metals projects are forward looking statements and can generally be ident ified
by the use of words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘m ay’, ‘should’, ‘will’ or
similar expressions. There can be no assurance that the OD6 Metals plans for its projects will proceed as expected and there can be
no assurance of future events which are subject to risk, uncertainties and other actions that may c ause OD6 Metals actual results,
performance, or achievements to differ from those referred to in this document. While the information contained in this docum ent
has been prepared in good faith, there can be given no assurance or guarantee that the occurren ce of these events referred to in
the document will occur as contemplated. Accordingly, to the maximum extent permitted by law, OD6 Metals and any of its affil iates
and their directors, officers, employees, agents and advisors disclaim any liability whethe r direct or indirect, express or limited,
contractual, tortuous, statutory or otherwise, in respect of, the accuracy, reliability or completeness of the information in this
document, or likelihood of fulfilment of any forward -looking statement or any event or results expressed or implied in any forward looking statement; and do not make any representation or warranty, express or implied, as to the accuracy, reliability or
completeness of the information in this document, or likelihood of fulfilment of any forward-looking statement or any event or
results expressed or implied in any forward -looking statement; and disclaim all responsibility and liability for these forward -looking
statements (including, without limitation, liability for negligence).
No new information
Except where explicitly stated, this announcement contains references to prior exploration results, all of which have been cr ossreferenced to previous market announcements made by the Company. The Company confirms that it is not aware of any new
information or data that materially affects the information included in the relevant market announcements.
The information in this report relating to the Mineral Resource estimate for the Splinter Rock Project is extracted from the
Company’s ASX announcements dated 24 May 2024. OD6 confirms that it is not aware of any new information or data that
materially affects the information included in the original announcement and that all material assumptions and technical parameters
underpinning the Mineral Resource estimate continue to apply
This announcement has been authorised for release by the Board of OD6 Metals Limited
8
About OD6 Metals
OD6 Metals is an Australian public company pursuing exploration and development opportunities within the
critical minerals sector, namely rare earths and copper.
Rare Earth Elements
OD6 Metals has successfully identified clay hosted rare earths at its 100% owned Splinter Rock Project which is
located in the Esperance-Goldfields region of Western Australia.
The Company released a Mineral Resource Estimate (MRE) for Splinter Rock in May 2024, confirming that the
project hosts one of the largest and highest-grade clay-hosted rare earths deposits in Australia with an
Indicated Resource of 119Mt @ 1,632ppm TREO and an Inferred Resource of 563Mt @ 1,275ppm TREO with an
overall ratio of ~23% high-value Magnetic Rare Earths (MagREE).
OD6 Metals believes that Splinter Rock has all the hallmarks of a world class rare earths project with a
conceptual heap leach development which utilises the large and high-grade Splinter Rock resource to support a
long-life REE operation.
Copper
The Company is advancing the Gulf Creek Copper-Zinc VMS Project located near the town of Barraba in NSW,
Australia.
Gulf Creek was mined at around the turn of the 20th century and was once regarded as the highest-grade
copper mine (2% to 6.5% Cu) in NSW until its closure due to weak copper prices in 1912. Very little exploration
has occurred at the project in over 100 years, with OD6 aiming to apply modern day exploration technologies.
The 2025 maiden drilling program successfully defined high grade copper below the historical mine plus
confirmed the strong relationship between magnetism and massive sulphide mineralisation. Geophysical
modelling has identified multiple, high priority and untested targets ready for drilling providing over >3km of
untested strike in the immediate mine-stratigraphy, and over >10km across the tenement.
Corporate Directory
Managing Director
Mr Brett Hazelden
Non-Executive Chairman
Mr Piers Lewis
Non-Executive Director
Dr Mitch Loan
Financial Controller/ Joint Company Secretary
Mr Troy Cavanagh
Joint Company Secretary
Mr Joel Ives
Contact
Investor Relations
OD6 Metals Ltd
Lucas Robinson
ACN 654 839 602
Corporate Storytime
www.od6metals.com.au
lucas@corporatestorytime.com
Mail to: info@od6metals.com.au
Phone: +61 408 228 889
Phone: +61 8 6189 8515
Level 1, 1 Alvan Street, Subiaco, WA 6008
9
Metallurgical Sample Selection and Testing Approach
The Company has created a composite sample for the Inside Centre that represent an area of consistent
geology, prior metallurgical outcomes, low striping ratios and significant grades.
A total 6 holes were selected (see table below) to composite at Inside Centre with samples combined by weight
to reflect the intercept length to maintain representativity and minimise any bias.
Column (Heap) Leach tests agglomerated the samples with a small amount of flocculant (~300g/t) to wet the
ore and bind the fines together. They are then irrigated with 25 g/l HCl lixiviant and run at ANSTO’s standard
column operating conditions for the duration of the tests. The column tests were conducted over an 80 day
period with samples still extracting rare earths at the end of this period.
Metallurgical Composite Drill Hole Location Details – Inside Centre Deposit
Hole ID
Type
Easting
Northing
RL (m)
Dip
(degrees)
Depth(s)
SRAC0225
Aircore
501815
6336021
204.1
-90
33-86
SRAC0226
Aircore
501953
6335879
204.4
-90
21-81
SRAC0266
Aircore
501399
6336445
205.4
-90
21-58
SRAC0357
Aircore
502068
6336999
204.9
-90
39-90
SRAC0358
Aircore
502177
6336615
204.0
-90
36-84
SRAC0359
Aircore
501939
6336293
203.5
-90
27-87
Figure 6: Inside Centre Composite Sample Locations overlain on airborne electromagnetic survey interpretation
10
JORC 2012 – Table1: Splinter Rock
Section 1 Sampling Techniques and Data
(Criteria listed in the preceding section also apply to this section)
Criteria
JORC Code explanation
Commentary
Sampling techniques
•
•
•
•
•
Drilling techniques
Drill sample recovery
•
•
•
•
Logging
•
•
•
Sub-sampling techniques
and sample preparation
•
•
•
•
Nature and quality of sampling (eg cut
channels, random chips, or specific
specialised industry standard
measurement tools appropriate to the
minerals under investigation, such as
down hole gamma sondes, or handheld
XRF instruments, etc). These examples
should not be taken as limiting the broad
meaning of sampling.
Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any
measurement tools or systems used.
Aspects of the determination of
mineralisation that are Material to the
Public Report.
In cases where ‘industry standard’ work
has been done this would be relatively
simple (eg ‘reverse circulation drilling was
used to obtain 1 m samples from which 3
kg was pulverised to produce a 30 g
charge for fire assay’). In other cases more
explanation may be required, such as
where there is coarse gold that has
inherent sampling problems. Unusual
commodities or mineralisation types (eg
submarine nodules) may warrant
disclosure of detailed information.
Drill type (eg core, reverse circulation,
open-hole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (eg core
diameter, triple or standard tube, depth of
diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by
what method, etc).
Method of recording and assessing core
and chip sample recoveries and results
assessed.
Measures taken to maximise sample
recovery and ensure representative nature
of the samples.
Whether a relationship exists between
sample recovery and grade and whether
sample bias may have occurred due to
preferential loss/gain of fine/coarse
material.
Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate
Mineral Resource estimation, mining
studies and metallurgical studies.
Whether logging is qualitative or
quantitative in nature. Core (or costean,
channel, etc) photography.
The total length and percentage of the
relevant intersections logged.
If core, whether cut or sawn and whether
quarter, half or all core taken.
If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet
or dry.
For all sample types, the nature, quality
and appropriateness of the sample
preparation technique.
Quality control procedures adopted for all
sub-sampling stages to maximise
representivity of samples.
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Geochemical sampling was undertaken by sampling of
metre interval samples returned from the cyclone of a
conventional air core drilling rig.
Certified reference samples, duplicates and blank
samples were inserted into the drill sample stream such
as to represent approximately 5% of the samples
submitted to the laboratory for analysis
Two composite samples were collected over three metre
intervals – the first (the A sample) being submitted for
laboratory analysis and the second (the B sample) being
retained as a reference.
A sample from each metre was collected and stored in a
chip tray for logging and x-ray diffraction analysis.
Drill intercept samples for the two heap leaching
metallurgical composites were obtained from the ‘B’
samples located on the company’s Exploration Licenses.
Samples were sent to ANSTO for making up the
composites and completing the testwork.
Air core drilling was completed by hammer and blade
industry standard drilling techniques
Aircore is considered to be an appropriate drilling
technique for saprolite clay
Drilling used blade bits of 87mmØ with 3m length drill
rods to blade refusal.
Air core recoveries were not recorded but are not
considered to be materially biased, given the nature of
the geology and samples.
The assay data will be analysed against control samples
and historical assays for any indications of bias
All chips were logged qualitatively and quantitatively.
A sample from each metre was collected and stored in a
chip tray for logging
Geological logs recorded lithology, colour and
weathering.
A composite sample of ~ 3kg for analysis was taken
using a scoop from each metre pile to subsample 1 to
1.5kg sample. This was then dispatched to the
laboratory.
A second composite sample was similarly taken and
stored on site as a reference
Air core samples were a mix of wet and dry
Certified reference samples, duplicates and blank
samples were inserted into the sample stream such as
to represent approximately 5% of the samples submitted
to the laboratory for analysis
11
Criteria
JORC Code explanation
Commentary
•
Measures taken to ensure that the
sampling is representative of the in situ
material collected, including for instance
results for field duplicate/second-half
sampling.
Whether sample sizes are appropriate to
the grain size of the material being
sampled.
The nature, quality and appropriateness of
the assaying and laboratory procedures
used and whether the technique is
considered partial or total.
For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the
analysis including instrument make and
model, reading times, calibrations factors
applied and their derivation, etc.
Nature of quality control procedures
adopted (eg standards, blanks, duplicates,
external laboratory checks) and whether
acceptable levels of accuracy (ie lack of
bias) and precision have been established.
•
The verification of significant intersections
by either independent or alternative
company personnel.
The use of twinned holes.
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
Discuss any adjustment to assay data.
•
•
Quality of assay data
and laboratory tests
•
•
•
Verification of sampling
and assaying
•
•
•
•
Heap Leach test samples were composited from the B
samples by weight to reflect the intercept length to
maintain representativity and minimise any bias
•
“A Samples” were submitted for chemical analysis using
industry standard sample preparation and analytical
techniques including:
•
Riffle split all “A samples” to 50:50 bagging one half
as a coarse reject for storage
•
Pulverise the balance of the material via LM-5
•
Generate a standard 300g master pulp packet
•
Bag the balance as a bulk pulp master for storage
• Multi-Element Ultra Trace method ME-MS61r for
exploration in soils or sed
Share your feedback
Discover