Major Flowsheet Improvements at Splinter Rock
Released
Released
Announcement PDF
ASX Announcement
2 September 2025
ASX: OD6
MAJOR FLOWSHEET IMPROVEMENTS
AT SPLINTER ROCK RARE EARTH PROJECT
CPC Engineering confirms the inclusion of a Chlor-Alkali Facility (CAF) as a key
development, delivering operating cost savings and strengthening projects economics
Highlights:
•
Chlor-Alkali Facility (CAF) confirmed as a cost-reduction measure, producing key reagents
onsite and materially lowering operating costs
•
Onsite production of Hydrochloric Acid (HCl) and Sodium Hydroxide (NaOH) eliminates
expensive transport of liquid reagents from Perth (~800km) reducing environmental footprint
•
Abundant and low-cost solar sea salt (NaCl), extensively produced in Western Australia,
provides the primary feedstock alongside water and energy
•
Expected to improve financial metrics through lower reagent costs and reduced logistics
•
High-quality Mixed Rare Earth Hydroxide (MREH ~59% TREO) already demonstrated using
onsite NaOH as a precipitation agent
•
CAF enables potential selective production of Nd, Pr, Dy, Tb oxides via a chloride-based
Solvent Extraction (SX) process
•
Strategic partnerships with ANSTO and CPC Engineering continue to guide the Optioneering
Study toward selection of the optimal development pathway
•
Drill campaign commencing shortly to supply additional material for ANSTO testwork
Managing Director Brett Hazelden, commented:
“The study conducted, in collaboration with CPC Engineering, confirms that the use of a Chlor-Alkali Facility (CAF)
to produce our reagent needs onsite will add substantial value at Splinter Rock. The modest capital cost is strongly
outweighed by the substantial savings in operating costs, driving a significant uplift in project economics.
Importantly, having a CAF on site not only reduces operating costs but also unlocks strategic flexibility, providing
the two critical reagents required for a chloride-based Solvent Extraction process capable of selectively producing
Nd, Pr, Dy and Tb oxides. This outcome would enable 100% payability for those high-value products.
The Optioneering process is well advanced, benchmarking multiple technically viable flowsheets to determine the
optimal economic, scalable, and sustainable development path forward.”
MagREE (Magnet Rare Earths) = Nd + Pr + Tb + Dy)
MagREO (Magnet Rare Earth Oxide) = Nd2 O3 + Pr6 O11 + Tb4 O7 + Dy2 O3
TREO (Total Rare Earth Oxide) = La2 O3 + CeO2 + Pr6 O11 + Nd2 O3 + Sm2 O3 + Eu2 O3 + Gd2 O3 + Tb4 O7 + Dy2 O3 + Ho2 O3 + Er2 O3 + Tm2 O3 + Yb2 O3 + Lu2 O3 + Y2 O3.
OD6 Metals Limited (OD6 or the Company) is pleased to report the first outcomes of the CPC
Optioneering Study which is assessing the metallurgical testwork outcomes conducted by the
Australian Nuclear Science and Technology Organisation (ANSTO). The work is evaluating the
multiple technically viable flowsheets, to enable the techno economic assessment of each
flowsheet. This study will identify a preferred flowsheet based on cost, recovery, scalability, and
product quality for the Splinter Rock Rare Earth Project.
What is a Chlor-Alkali Facility?
A Chlor-Alkali Facility (CAF) is a plant that produces two essential chemicals, Hydrochloric Acid (HCl) and
Sodium Hydroxide (NaOH), from Salt (NaCl) and Water:
How It Works
The Chlor-Alkali process relies on electrolysis, splitting salt (NaCl) dissolved in water into its components.
In short, an electric current passes through the salt brine to produce hydrogen, chlorine and sodium hydroxide.
The hydrogen and chlorine can then be combined into hydrochloric acid.
The equations to create sodium hydroxide (NaOH) and hydrochloric acid (HCl) are:
2H2O (l) + 2NaCl (aq) —-> H2 (g) + Cl2 (g) + 2NaOH (aq)
H2 (g) + Cl2 (g) —–> 2HCl (g)
Figure 1: Example of two BICHLOR™ Electrolysers utilised to produce H2 (g) + Cl2 (g) + 2NaOH (aq)
2
Strategic Importance for Splinter Rock
HCl and NaOH are essential reagents used by OD6:
1. Heap Leaching with HCl extracts rare earths into solution (refer ASX 16 October 2024)
2. Importantly over 80% of HCl can recycled using NanoFiltration (refer ASX 4 August 2025)
3. NaOH is utilised in impurity removal and precipitation
4. NaOH is also use to precipitate a Mixed Rare Earth Hydroxide (MREH) (refer ASX 13 August 2025).
By producing these reagents onsite, OD6 avoids costly liquid transport, secures supply reliability, and reduces
environmental footprint.
Technical Review
CPC Engineering (CPC) and OD6 have undertaken a technical and cost review of reagent requirements and the
most cost effective source for the Splinter Rock Rare Earth Project located Northwest of Esperance in Western
Australia.
The two Main reagent souring options for the project include:
•
Purchasing liquid HCl and NaOH from Kwinana (~800km away). This has been determined to not be
financially viable due to significant transport volumes and costs.
•
Importing solar sea salt (NaCl) and converting it to HCl and NaOH in a CAF. Salt is abundantly
produced in WA’s northwest and would be shipped to Esperance Port, then trucked ~150km to site. This
has been determined to be a far more cost-effective solution.
Indicative vendor provided information utilising a BICHLOR™ Electrolyser confirms:
•
Modest capital cost (~A$6M per electrolyser unit).
•
Single unit capacity sufficient to treat up to 5–6Mtpa of clay ore.
•
Up to 62ktpa HCl and 69ktpa NaOH production capacity.
•
Power consumption ~1,990kWh/te NaOH (major cost input).
OD6 is investigating powering the CAF via a hybrid renewable energy system (solar, wind, storage, plus backup
gas/diesel generation).
ANSTO Metallurgical Outcomes to Date
As part of its advanced metallurgical program, OD6 and ANSTO has successfully demonstrated a multi-stage
processing pathway (Figure 2) that efficiently extracts and purifies rare earth elements from Splinter Rock’s
clay-hosted deposits. The flowsheet consists of:
1.
Heap Leaching – Simple, low-acid usage leaching of rare earth-bearing clays to generate enriched
leachate solution (refer ASX 16 October 2024)
2.
Nanofiltration (NF) – Recycling of Acid, concentration of REEs and reduction of liquid volume
produced downstream (refer ASX 4 August 2025)
3
3.
Ion Exchange (IX) – Concentration of rare earth elements and enhanced removal of iron (Fe) and
aluminium (Al) reducing downstream processing risk (refer ASX 7 August 2025)
4.
Impurity Removal (IR) – Final removal of residual deleterious elements (e.g. Al, Ca, Fe, U, Th, P) to meet
high product quality and low impurity specifications.
5.
Product Precipitation – Recovery of high-grade Mixed Rare Earth Carbonate (MREC) or Hydroxide
(MREH) from purified solution (refer ASX 13 August 2025)
The final MREC/MREH products contain elevated concentrations of Nd, Pr, Dy and Tb, collectively representing
a high-value magnetic rare earth mix highly sought after in permanent magnet supply chains. Benchmark
payability for MREC and MREH typically ranges between 70–85% of REO basket value.
Figure 2: Indicative processing steps including Heap Leach, Nanofiltration plus Ion Exchange &Impurity Removal
Selective Nd, Pr, Tb and Dy Oxide Production Potential
Whilst initial development at Splinter Rock targets MREC or MREH, the onsite CAF positions OD6 for potential
future production of individual oxides (Nd, Pr, Dy, Tb) through a chloride-based SX process. Discussions with
ANSTO are ongoing as part of the Optioneering Study.
Next Steps
Optioneering Study: CPC Engineering (CPC) and ANSTO are continuing to review the testwork performed over
the last 9 months as part of an Optioneering Study. The study is evaluating the multiple technically viable
flowsheets, to enable the techno economic assessment of each flowsheet. This study will identify a preferred
flowsheet based on cost, recovery, scalability, and product quality.
Engagement with potential offtake partners: to assess commercial payability options for MREC and MREH
products.
Engagement with government and potential financing partners: OD6 has and continues to engage
government and potential financing organisations. This is anticipated to be a continuous process over the
development cycle.
Testwork Drill Campaign: OD6 is currently engaging drilling contracts to commence in September to
undertake twin holed diamond core material of the original 6 holes. Six HQ or PQ drill holes (63 to 85mm core)
will be drilled to provide 1.5 to 2.5 tonne of REE bearing material for testwork to be conducted ant ANSTO.
ANSTO Testwork Scale Up: Heap Leach and Impurity Removal testwork would be scaled up by utilising twin
holed diamond core material of the original 6 holes. Bulk testing 1 tonne of REE bearing material, which can be
utilised to conduct multiple optimisation and validation tests findings from the current reported testwork. This
volume would also produce ~1kg of MREC which would enable multiple samples to be produced for testing and
offtake discussions.
4
Forward Looking Statements
Certain information in this document refers to the intentions of OD6 Metals, however these are not intended to be forecasts,
forward looking statements, or statements about the future matters for the purposes of the Corporations Act or any other
applicable law. Statements regarding plans with respect to OD6 Metals projects are forward looking statements and can
generally be identified by the use of words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘aim’, ‘intend’, ‘anticipate’, ‘b elieve’,
‘estimate’, ‘may’, ‘should’, ‘will’ or similar expressions. There can be no assurance that the OD6 Metals plans for its projects
will proceed as expected and there can be no assurance of future events which are subject to risk, uncertainties and other
actions that may cause OD6 Metals actual results, performance, or achievements to differ from those referred to in this
document. While the information contained in this document has been prepared in good faith, there can be given no
assurance or guarantee that the occurrence of these events referred to in the document will occur as contemplated.
Accordingly, to the maximum extent permitted by law, OD6 Metals and any of its affiliates and their directors, officers,
employees, agents and advisors disclaim any liability whether direct or indirect, express or limited, contractual, tortuous,
statutory or otherwise, in respect of, the accuracy, reliability or completeness of the information in this document, or
likelihood of fulfilment of any forward-looking statement or any event or results expressed or implied in any forward-looking
statement; and do not make any representation or warranty, express or implied, as to the accuracy, reliability or
completeness of the information in this document, or likelihood of fulfilment of any forward-looking statement or any event
or results expressed or implied in any forward-looking statement; and disclaim all responsibility and liability for these
forward-looking statements (including, without limitation, liability for negligence).
No new information
Except where explicitly stated, this announcement contains references to prior exploration results, all of which have been
cross-referenced to previous market announcements made by the Company. The Company confirms that it is not aware of
any new information or data that materially affects the information included in the relevant market announcements.
The information in this report relating to the Mineral Resource estimate for the Splinter Rock Project is extracted from the
Company’s ASX announcements dated 18 July 2024. OD6 confirms that it is not aware of any new information or data that
materially affects the information included in the original announcement and that all material assumptions and technical
parameters underpinning the Mineral Resource estimate continue to apply
This announcement has been authorised for release by the Board of OD6 Metals Limited
5
About OD6 Metals
OD6 Metals is an Australian public company pursuing exploration and development opportunities within the
critical minerals sector, namely rare earths and copper.
Rare Earth Elements
OD6 Metals has successfully identified clay hosted rare earths at its 100% owned Splinter Rock Project which is
located in the Esperance-Goldfields region of Western Australia.
The Company released a Mineral Resource Estimate (MRE) for Splinter Rock in May 2024, confirming that the
project hosts one of the largest and highest-grade clay-hosted rare earths deposits in Australia with an
Indicated Resource of 119Mt @ 1,632ppm TREO and an Inferred Resource of 563Mt @ 1,275ppm TREO with an
overall ratio of ~23% high-value Magnetic Rare Earths (MagREE).
OD6 Metals believes that Splinter Rock has all the hallmarks of a world class rare earths project with a
conceptual heap leach development which utilises the large and high-grade Splinter Rock resource to support a
long-life REE operation.
Copper
The Company is advancing the Gulf Creek Copper-Zinc VMS Project located near the town of Barraba in NSW,
Australia.
Gulf Creek was mined at around the turn of the 20th century and was once regarded as the highest grade
copper mine (2% to 6.5% Cu) in NSW until its closure due to weak copper prices in 1912. Very little exploration
has occurred at the project in over 100 years, with OD6 aiming to apply modern day exploration technologies.
The 2025 maiden drilling program successfully defined high grade copper below the historical mine plus
confirmed the strong relationship between magnetism and massive sulphide mineralisation. Geophysical
modelling has identified multiple, high priority and untested targets ready for drilling providing over >3km of
untested strike in the immediate mine-stratigraphy, and over >10km across the tenement.
Corporate Directory
Managing Director
Mr Brett Hazelden
Non-Executive Chairman
Non-Executive Director
Mr Piers Lewis
Dr Mitch Loan
Financial Controller/ Joint Company Secretary
Mr Troy Cavanagh
Joint Company Secretary
Mr Joel Ives
Contact
Investor Relations
OD6 Metals Ltd
Lucas Robinson
ACN 654 839 602
Corporate Storytime
www.od6metals.com.au
Mail to: info@od6metals.com.au
lucas@corporatestorytime.com
Phone: +61 408 228 889
Phone: +61 8 6189 8515
Level 1, 1 Alvan Street, Subiaco, WA 6008
6