OD6 APPOINTS PERMITTING TEAM AT QUINN FLUORSPAR PROJECT
Released
Released
Announcement PDF
ASX Announcement
2 June 2026
ASX: OD6
1
OD6 APPOINTS WESTLAND AS PERMITTING CONSULTANTANT
TO ACCELERATE QUINN FLUORSPAR PROJECT, NEVADA
OD6 Metals Limited (ASX: OD6) (“OD6” or “the Company”) is pleased to announce the
appointment of WestLand Engineering & Environmental Services (“WestLand”) as permitting
consultant for its Quinns Fluorspar Project (“Project”) in Nevada, USA.
HIGHLIGHTS
• Tier-1 U.S. permitting consultant appointed with extensive USFS, NEPA and Fast 41 experience
• WestLand has been engaged to manage permitting and environmental baseline programs under the
United States Forest Service (“USFS”) framework, supporting a streamlined pathway from exploration
through to potential development
• A front-end loading permitting approach is being undertaken with all current claims being fully
surveyed which can be utilised across a 10 year validity period inclusive of drill and mine permitting.
• The requisite Pre-Plan Letter introducing the Project and proposed exploration activities has been
submitted during May 2026
• Seasonal biological and archaeological baseline surveys will be completed in the coming months
• Targeting Categorical Exclusion (CE) to enable the maiden drilling program to occur
• A Plan of Operations (POO) and other required supporting documentation will be submitted to the USFS
• Bulk sampling program is planned to supportmetallurgical testwork across multiple target areas within
the Project Area
• This approach positions OD6 to avoid duplication of studies and significantly streamline future
permitting requirements
• Alignment with U.S. critical minerals policy and FAST-41 permitting framework potential
Managing Director Brett Hazelden, commented:
"The appointment of WestLand marks a critical step in accelerating the Quinns Fluorspar Project through the
U.S. permitting process.
By front-end loading environmental baseline studies,we are positioning the Project fora streamlined approval
pathway, while aligning with U.S. critical minerals policy and potential FAST-41 pathways.
Importantly, this work also underpins our ability to pursue bulk sampling and metallurgical testwork,
advancing the Project toward development."
2
Permitting Strategy – Front End Loading Approach
OD6 has adopted a proactive permitting strategy designed to streamline project requirements and reduce
future approval risk.
Westland is a Tier-1 U.S. permitting consultant with extensive USFS, NEPA and Fast 41 experience.
WestLand will undertake:
• Class III cultural (archaeological) survey
• Comprehensive biological baseline surveys (flora & fauna)
• Supporting environmental and regulatory documentation under National Environmental Policy ACT
(NEPA)
Importantly, these baseline surveys are expected to have validity of up to 10 years, enabling their use and support
for the following permitting actions:
• Initial POO application
• Expanded POO submission
• Potential mining and development POO submission
This approach positions OD6 to avoid duplication of studies and significantly compress future permitting
timelines.
Initial Drilling – POO with Approval Under Categoric Exclusion (CE)
The Company is targeting an initial drill program under a POO with approval via CE with the USFS.
The CE approval pathway is designed for low-impact exploration activities, typically including:
• Less than 1 mile (~1.6km) of new access roads
• Less than 5 acres (~2 hectares) of surface disturbance
• One year to complete exploration and corresponding reclamation activities
OD6 has submitted initial concepts including drill pads, access routes and associated infrastructure consistent with
CE thresholds. OD6 will coordinate closely with the USFS to complete applications and baseline studies required
for federal approvals.
Plan of Operations (POO) – Expanded Drilling Pathway analysed and approved under an
Environmental Assessment (EA) with Corresponding Reclamation Permit
In parallel with the CE application, OD6 intends to scale exploration under an expanded POO. The POO will:
• Enable expanded drilling programs beyond one mile of constructed road and 5 acres of surface
disturbance
• Support resource definition and step-out exploration
• Incorporate biological and cultural baseline data collected in 2026
• Be formatted to include sections in compliance with Nevada State Regulations, required for Projects
exceeding 5 acres of surface disturbance
The Company will leveraging early baseline work to streamline assessment and approvals.
3
Bulk Sampling and Metallurgical Testwork
As part of the drilling approvals, OD6 intends to:
• Apply for bulk sampling permits across multiple areas
• Extract representative material for metallurgical testwork and flowsheet optimisation
This strategy aligns with recent U.S. project precedents where bulk sampling has:
• Accelerated development pathways
• Supported offtake and processing discussions
• Reduced technical and commercial risk
Strong Alignment with US Policy and Fast-41 Potential
The Project is strongly aligned with U.S. Government priorities to secure domestic critical mineral supply chains,
including fluorspar.
Recent developments in U.S. policy include:
• Ongoing efforts by the USFS to streamline permitting processes, including clearer thresholds and
faster environmental reviews
• Increased federal focus on critical minerals supply security
• Expansion of frameworks such as FAST-41, designed to accelerate permitting of strategic infrastructure
projects (refer FAST-41 Program | Permitting Council)
FAST-41 designation provides:
• Coordinated federal agency approvals
• Defined permitting timelines and transparency
• Potential for accelerated development outcomes
OD6 believes the Quinns Project is well positioned to benefit from these initiatives, particularly given its:
• Location on U.S. federal land
• Critical mineral exposure (fluorspar)
• Near-term development potential
An initial discussion with a Fast-41 representative has occurred, with the Fast 41 Transparency program being
most applicable for the project, with further consideration after submission of the baseline studies and POO.
Next Steps - Permitting
• biological and cultural surveys have commenced (2026 field season)
• Finalise and submit initial phase POO application
• Target CE approval and drilling as soon as practicable
• Advance POO for expanded drilling
• Progress bulk sampling permit applications
4
Forward Looking Statements
Certain information in this document refers to the intentions of OD6 Metals, however these are not intended to
be forecasts, forward looking statements, or statements about the future matters for the purposes of the
Corporations Act or any other applicable law. Statements regarding plans with respect to OD6 Metals projects
are forward looking statements and can generally be identified by the use of words such as ‘project’, ‘foresee’,
‘plan’, ‘expect’, ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar expressions. There
can be no assurance that the OD6 Metals plans for its projects will proceed as expected and there can be no
assurance of future events which are subject to risk, uncertainties and other actions that may cause OD6 Metals
actual results, performance, or achievements to differ from those referred to in this document. While the
information contained in this document has been prepared in good faith, there can be given no assurance or
guarantee that the occurrence of these events referred to in the document will occur as contemplated.
Accordingly, to the maximum extent permitted by law, OD6 Metals and any of its affiliates and their directors,
officers, employees, agents and advisors disclaim any liability whether direct or indirect, express or limited,
contractual, tortuous, statutory or otherwise, in respect of, the accuracy, reliability or completeness of the
information in this document, or likelihood of fulfilment of any forward-looking statement or any event or
results expressed or implied in any forward-looking statement; and do not make any representation or warranty,
express or implied, as to the accuracy, reliability or completeness of the information in this document, or
likelihood of fulfilment of any forward-looking statement or any event or results expressed or implied in any
forward-looking statement; and disclaim all responsibility and liability for these forward-looking statements
(including, without limitation, liability for negligence).
No new information
Except where explicitly stated, this announcement contains references to prior exploration results, all of which
have been cross-referenced to previous market announcements made by the Company. The Company confirms
that it is not aware of any new information or data that materially affects the information included in the
relevant market announcements.
The information in this report relating to the Mineral Resource estimate for the Splinter Rock Project is extracted
from the Company’s ASX announcements dated 18 July 2024. OD6 confirms that it is not aware of any new
information or data that materially affects the information included in the original announcement and that all
material assumptions and technical parameters underpinning the Mineral Resource estimate continue to apply.
This announcement has been authorised for release by the Board of OD6 Metals Limited
5
About OD6 Metals
OD6 Metals Ltd is an Australian critical minerals exploration and development company with projects spanning fluorspar,
rare earth elements and copper across the United States and Australia.
OD6 aims to position itself as an emerging supplier of strategically important critical minerals required for next-generation
industrial, defence and energy technologies.
Quinn Fluorspar Project – Nevada, USA
OD6 is advancing the Quinn Fluorspar Project located in Nevada, USA, one of the world’s premier mining jurisdictions and
currently ranked second globally in the Fraser Institute 2025 Mining Attractiveness Index.
Quinn hosts multiple high-grade fluorspar deposits including Horseshoe, Mammoth and Big Jim, with historical drilling,
channel sampling and testwork confirming significant high-grade mineralisation and potential for both Metspar and
premium Acidspar products.
Fluorspar is classified as a critical mineral in the United States, which currently imports 100% of all Fluorspar consumed
domestically with >60% of all global supply sourced from China. It is essential in hydrofluoric acid production, AI
semiconductor manufacturing, advanced battery technologies, uranium enrichment defence systems and refrigerants.
Splinter Rock Rare Earth Project – Western Australia
OD6’s 100% owned Splinter Rock Rare Earth Project in Western Australia hosts one of Australia’s largest and highest-grade
clay-hosted rare earth deposits, with a Mineral Resource Estimate of:
• Indicated: 119Mt @ 1,632ppm TREO
• Inferred: 563Mt @ 1,275ppm TREO
OD6 is advancing an innovative processing flowsheet utilising heap leaching, nanofiltration and ion exchange technologies
designed to achieved ~75% Nd & Pr overall recovery plus produce a high-quality Mixed Rare Earth Carbonate/Hydroxide
product of ~56-59% TREO with low impurity levels
Gulf Creek Copper Project – New South Wales
OD6 is also advancing the Gulf Creek Copper-Zinc VMS Project in New South Wales, a historically high-grade copper mining
district with significant exploration upside.
Recent drilling and geophysical programs have confirmed high-grade copper mineralisation and identified multiple large-
scale exploration targets along more than 10km of prospective strike.
Corporate Directory
Managing Director
Non-Executive Chairman
Non-Executive Director
Financial Controller/ Joint Company Secretary
Joint Company Secretary
Technical Advisor to the Board
Contact
OD6 Metals Ltd
ACN 654 839 602
www.od6metals.com.au
Mail to: info@od6metals.com.au
Phone: +61 8 6189 8515
Level 1, 1 Alvan Street, Subiaco, WA 6008
Mr Brett Hazelden
Mr Piers Lewis
Dr Mitch Loan
Mr Troy Cavanagh
Mr Joel Ives
Dr Darren Holden
Investor Relations
Lucas Robinson
Corporate Storytime
lucas@corporatestorytime.com
Phone: +61 408 228 889
Share your feedback
Discover