MAIDEN QUINN DRILLING BULK SAMLPLING PERMIT SUBMITTED
Released
Released
Announcement PDF
ASX Announcement
15 September 2026
ASX: OD6
1
MAIDEN DRILLING & BULK SAMPLING PERMIT APPLICATION
SUBMITTED AT QUINN FLUORSPAR PROJECT
139 drill pads proposed as biological and cultural surveys completed with
OD6 targeting streamlined U.S. federal permitting pathway
HIGHLIGHTS
• Major permitting milestone achieved: Plan of Operations (“PoO”) submitted to the U.S. Forest Service
(“USFS”) seeking approval for OD6’s maiden drilling and bulk-sampling program at the 100%-owned
Quinn Fluorspar Project in Nevada, USA
• Extensive high-grade fluorspar mineralisation identified from surface remains largely untested by
drilling, with only four shallow historical drill holes at Horseshoe and the proposed program designed
to systematically test the Horseshoe–Mammoth mineralised trend along strike and at depth.
• PoO provides for up to 139 drill pads across priority Quinn target areas, with the flexibility to
complete multiple drill holes from individual pads
• Proposed drilling is designed to establish the geological, grade and continuity data required to support
a future Mineral Resource Estimate
• PoO also seeks approval for bulk sampling of representative fluorspar mineralisation to support larger-
scale ore sorting, beneficiation and metallurgical testwork
• All planned biological and cultural baseline field surveys are complete, with final reports targeted for
submission to the USFS in October 2026, materially advancing the environmental review process
• OD6 is targeting approval through a Categorical Exclusion pathway, providing a potentially streamlined
federal environmental review pathway for the proposed exploration activities
• Potential future FAST-41 Transparency status for Quinn, which could provide enhanced transparency
on federal permitting process
Managing Director Brett Hazelden, commented:
"Submission of the Plan of Operations is a major milestone for Quinn and moves OD6 another important step closer
to drilling what we consider to be an exceptional high-grade U.S. fluorspar opportunity.
This is much more than an application to drill. The PoO has been designed to provide the permitting framework to
systematically define the high-grade fluorspar systems at Quinn and obtain representative bulk material required
to advance our metallurgical and beneficiation programs.
With up to 139 drill pads, around 10,000m of priority 1 drilling and the ability to complete multiple holes from
individual pads, the proposed program provides substantial flexibility to undertake both resource-definition and
exploration drilling while minimising additional surface disturbance.
We have deliberately front-end loaded the permitting process, with all planned biological and cultural baseline field
surveys now completed at Horseshoe through to Mammoth. Our drilling strategy is designed to progressively
establish the geological, grade and continuity information required to support a future Mineral Resource Estimate.
2
The PoO will now progress through the USFS review process, with OD6 targeting a Categorical Exclusion pathway
for this initial phase. Submission also provides an important foundation for our ongoing engagement regarding
potential FAST-41 Transparency status, which, if subsequently granted, could provide additional federal coordination
and transparency as Quinn advances through the permitting process."
OD6 Metals Limited (ASX: OD6) (“OD6” or “the Company”) is pleased to advise that it has submitted a Plan
of Operations (“PoO”) to the United States Forest Service (“USFS”) seeking approval for a major drilling and
bulk-sampling program at the Company’s 100%-owned Quinn Fluorspar Project in Nevada, USA.
Maiden Drilling Program Proposed
The submitted PoO provides for up to 139 drill pads across the Quinn Fluorspar Project.
The proposed pad locations have been designed to provide flexibility across both resource-definition and
exploration targets and, where practicable, enable multiple drill holes to be completed from individual pads.
This approach is intended to:
• minimise overall surface disturbance associated with drilling
• maximise geological information obtained from individual drill locations
• allow mineralised structures to be tested at different depths and orientations
• provide flexibility to follow mineralisation based on progressive drilling results
• undertake systematic infill and resource-definition drilling
• enable step-out and exploration drilling within the permitted footprint
The proposed program will initially focus on the priority Horseshoe, Mammoth and Big Jim fluorspar areas,
together with other high-priority targets identified through OD6’s systematic geological mapping, geochemical
sampling, structural interpretation and review of historical exploration.
The PoO also seeks approval for bulk sampling from selected fluorspar mineralised areas, providing
representative material to support larger-scale ore sorting, beneficiation and comprehensive metallurgical
testwork.
Submission follows completion of the planned biological and cultural baseline field surveys across the Project
area and represents another major milestone in OD6’s strategy to front-end load environmental and permitting
activities at Quinn.
OD6 is targeting approval of the PoO through a Categorical Exclusion (“CE”) pathway, subject to assessment
and determination by the USFS.
Drilling Designed to Support Resource Definition
The proposed drilling represents an important transition for Quinn from surface exploration and target
generation towards systematic drill testing and resource definition.
The drilling program is designed to establish:
• geometry and orientation of the principal fluorspar mineralised zones
• mineralised widths and grade distribution
• geological and grade continuity along strike and at depth
• relationships between high-grade surface mineralisation and historical drilling
• potential extensions beyond currently defined mineralised areas
• representative material for ongoing mineralogical, beneficiation and metallurgical studies
3
Within the principal mineralised areas, OD6 intends to progressively establish drill spacing appropriate to
support future Mineral Resource Estimation.
Figure 1: Quinn Fluorspar Project – proposed PoO drill pad locations
4
Bulk Sampling to Advance Metallurgical Development
In addition to drilling, the PoO seeks approval for bulk sampling from selected Quinn fluorspar mineralised
areas to provide larger and more representative samples for ongoing metallurgical development.
The proposed bulk-sampling program is intended to provide representative material for:
• larger-scale ore sorting and sensor-based beneficiation testwork
• crushing, screening and physical beneficiation studies
• heavy-media and/or gravity separation testwork, where applicable
• grinding and flotation optimisation
• assessment of mineralogical and impurity deportment
• production of representative Metspar and/or Acidspar products for specification testing
• generation of larger product samples for potential downstream customer and strategic-partner
evaluation.
The bulk-sampling program will build on the Company’s current ore sorting and metallurgical testwork program
and is intended to progressively establish the flowsheet, recoveries, product specifications and operating
parameters required to assess potential commercial development pathways for Quinn.
Biological and Cultural Baseline Surveys Completed
OD6 has completed the biological baseline field surveys covering relevant flora and fauna plus
archaeological field surveys across the Quinn Project area required for environmental review of the Project.
The surveys were undertaken by specialist U.S. environmental and permitting consultant WestLand Engineering
& Environmental Services (“WestLand”) as part of the Company’s strategy to front-end load environmental
and permitting activities.
The final biological and cultural survey reports are expected to be provided to the USFS during October 2026 as
supporting information for its review of the PoO.
As previously announced, OD6 elected to undertake baseline surveys across a broader area than required solely
for the initial drilling program. This approach is designed to:
• provide environmental and cultural information to support the current PoO
• minimise requirements of future field studies
• support subsequent expansion of exploration activities
• support future bulk-sampling and metallurgical activities
• establish baseline information capable of supporting subsequent mine-development permitting
The completed surveys and supporting documentation provide an important environmental baseline for both
the current permitting process and future development activities at Quinn. These surveys can be utilised
across a 10 year validity period inclusive of drill and mine permitting.
5
Targeted Streamlined Federal Review Pathway
OD6 is targeting a streamlined federal environmental review pathway for the proposed exploration program
through a Categorical Exclusion ("CE") pathway, subject to assessment and determination by the U.S. Forest
Service (USFS).
A CE determination by the USFS exempts routine or low-impact mineral projects from detailed National
Environmental Policy Act (NEPA) environmental assessments or impact statements.
This phase of the Quinn exploration program has been designed with surface disturbance and access
requirements to maximize Project flexibility while maintaining eligibility for approval under a CE determination,
including the use of existing access where practicable and the ability to undertake multiple drill holes from
individual pads.
The USFS will assess the PoO and supporting environmental information and determine the appropriate
environmental review pathway, together with any additional information, mitigation measures, operating
conditions or financial assurance required.
USFS Review and Approval Process
Following submission, the PoO will progress through the USFS review and approval process under 36 CFR Part
228, Subpart A – Locatable Minerals.
The regulations provide an initial review framework under which the USFS assesses a submitted PoO and may
approve the plan, request modifications or additional information, determine that further review is required or
make other determinations provided for under the regulations.
OD6 anticipates the Quinn PoOwill broadly progress through the following stages:
Stage Status
PoO submitted to USFS
Drilling, bulk sampling, access, disturbance and reclamation plan
✓ Complete
Biological & cultural surveys
Fieldwork complete; final reports targeted for submission to
USFS in October 2026
✓ Fieldwork Complete
USFS review & environmental determination
Technical/environmental review, including determination of
appropriate NEPA pathway; OD6 targeting a CE
In Progress
Approval & mobilisation
Final operating conditions/bonding followed by commencement
of drilling and bulk sampling
Pending
Under the regulations, the USFS has an initial 30-day review period following receipt of a proposed PoO.
Depending on the outcome of that review, the USFS may request additional information or modifications, advise
that additional time is required, or determine that further environmental analysis is necessary.
6
Alignment with Fast-41 Transparency Status
Submission of the PoO establishes a defined federal permitting pathway for Quinn and supports OD6’s broader
engagement with U.S. Government agencies regarding the Project.
OD6 has undertaken initial engagement regarding the potential future inclusion of Quinn within the FAST-41
Transparency Program, administered by the U.S. Federal Permitting Improvement Steering Council (“Permitting
Council”).
Subject to future acceptance, FAST-41 Transparency Program status could provide enhanced coordination
between OD6, the USFS and other relevant federal agencies, together with a comprehensive permitting
timetable, public milestone tracking through the Federal Permitting Dashboard and access to a dedicated
Permitting Council project advisor.
FAST-41 does not remove or modify applicable environmental, consultation or regulatory requirements, nor
does it predetermine the outcome of any federal permitting decision.
No FAST-41 designation has presently been granted to Quinn and any future inclusion remains subject to
assessment and acceptance by the Permitting Council.
Delivering OD6’s Front End Loading Permitting Strategy
The PoO submission represents delivery against the permitting strategy previously outlined by OD6, under
which the Company elected to commence environmental, cultural and regulatory activities early in the
advancement of Quinn.
Permitting Milestone Status
Specialist U.S. permitting consultant WestLand appointed ✓ Complete
Initial engagement with U.S. Forest Service ✓ Complete
Pre-Plan Letter submitted to USFS ✓ Complete
Biological baseline field surveys ✓ Complete
Cultural baseline surveys ✓ Complete
Drill pads, bulk sampling and access designed ✓ Complete
Plan of Operations submitted ✓ Complete
USFS technical and environmental review Commencing
Categorical Exclusion pathway Targeted
Potential FAST-41 Transparency status Engagement Commenced
Drilling and bulk-sampling approvals Pending
Maiden OD6 drilling program and bulk-sampling approvals Following Approvals
The Company’s previous permitting announcement (refer ASX 2 June 2026) outlined its strategy to undertake
seasonal biological and cultural surveys early, progress engagement with the USFS and prepare the PoO to
enable drilling and future development activities. The current submission represents a significant progression of
that strategy.
7
Quinn Advancing on Multiple Fronts
The permitting submission occurs alongside a broader program designed to progressively de-risk and advance
the Quinn Fluorspar Project.
Key workstreams include:
• Exploration and resource definition – up to 139 drill pads proposed across priority targets, with multiple
holes possible from individual pads;
• Bulk sampling – approval sought for representative material to support larger-scale metallurgical
development;
• Permitting – PoO submitted and planned biological and cultural baseline field surveys completed;
• Ore sorting – evaluation of the potential to reject waste and upgrade mineralised feed prior to
downstream processing;
• Metallurgy – comprehensive beneficiation testwork evaluating pathways towards Metspar and premium
Acidspar products;
• U.S. Government engagement – ongoing engagement regarding relevant U.S. critical-minerals
initiatives and potential FAST-41 Transparency status; and
• Future development studies – progressively establishing the geological, metallurgical, environmental
and regulatory information required to assess potential development pathways.
Figure 2: Quinn Fluorspar Project – district claim position and project areas, Nevada USA
8
Figure 3: Quinn Fluorspar Location in Nevada with proximity to major gold trends
Next Steps
Following submission of the PoO, OD6 will work closely with WestLand and the U.S. Forest Service to progress
the application through the federal review process.
Near-term activities include:
• responding to any USFS requests for additional information or modifications
• progressing the targeted CE determination pathway
• finalising drill targeting and sequencing across the proposed 139 drill pads
• progressing State and other ancillary approvals required prior to drilling and bulk sampling
• continuing engagement regarding potential FAST-41 Transparency status
• continuing current ore sorting and comprehensive metallurgical testwork
• refining the proposed bulk-sampling and larger-scale metallurgical programs
• preparing for mobilisation of the maiden drilling program following receipt of all required approvals
9
References
1. OD6 Metals Limited, ASX Announcement, 2 June 2026 – previous Quinn permitting strategy announcement.
2. U.S. Forest Service – 36 CFR Part 228, Subpart A – Locatable Minerals.
3. U.S. Forest Service – National Environmental Policy Act procedures.
4. Federal Permitting Improvement Steering Council – FAST-41 Transparency Program.
Forward Looking Statements
Certain information in this document refers to the intentions of OD6 Metals, however these are not intended to
be forecasts, forward looking statements, or statements about the future matters for the purposes of the
Corporations Act or any other applicable law. Statements regarding plans with respect to OD6 Metals projects
are forward looking statements and can generally be identified by the use of words such as ‘project’, ‘foresee’,
‘plan’, ‘expect’, ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar expressions. There
can be no assurance that the OD6 Metals plans for its projects will proceed as expected and there can be no
assurance of future events which are subject to risk, uncertainties and other actions that may cause OD6 Metals
actual results, performance, or achievements to differ from those referred to in this document. While the
information contained in this document has been prepared in good faith, there can be given no assurance or
guarantee that the occurrence of these events referred to in the document will occur as contemplated.
Accordingly, to the maximum extent permitted by law, OD6 Metals and any of its affiliates and their directors,
officers, employees, agents and advisors disclaim any liability whether direct or indirect, express or limited,
contractual, tortuous, statutory or otherwise, in respect of, the accuracy, reliability or completeness of the
information in this document, or likelihood of fulfilment of any forward-looking statement or any event or
results expressed or implied in any forward-looking statement; and do not make any representation or warranty,
express or implied, as to the accuracy, reliability or completeness of the information in this document, or
likelihood of fulfilment of any forward-looking statement or any event or results expressed or implied in any
forward-looking statement; and disclaim all responsibility and liability for these forward-looking statements
(including, without limitation, liability for negligence).
No new information
Except where explicitly stated, this announcement contains references to prior exploration results, all of which
have been cross-referenced to previous market announcements made by the Company. The Company confirms
that it is not aware of any new information or data that materially affects the information included in the
relevant market announcements.
The information in this report relating to the Mineral Resource estimate for the Splinter Rock Project is extracted
from the Company’s ASX announcements dated 18 July 2024. OD6 confirms that it is not aware of any new
information or data that materially affects the information included in the original announcement and that all
material assumptions and technical parameters underpinning the Mineral Resource estimate continue to apply.
This announcement has been authorised for release by the Board of OD6 Metals Limited
10
About OD6 Metals
OD6 Metals Ltd is an Australian critical minerals exploration and development company with projects spanning fluorspar,
rare earth elements and copper across the United States and Australia.
OD6 aims to position itself as an emerging supplier of strategically important critical minerals required for next-generation
industrial, defence and energy technologies.
Quinn Fluorspar Project – Nevada, USA
OD6 is advancing the Quinn Fluorspar Project located in Nevada, USA, one of the world’s premier mining jurisdictions and
currently ranked second globally in the Fraser Institute 2025 Mining Attractiveness Index.
Quinn hosts multiple high-grade fluorspar deposits including Horseshoe, Mammoth and Big Jim, with historical drilling,
channel sampling and testwork confirming significant high-grade mineralisation and potential for both Metspar and
premium Acidspar products.
Fluorspar is classified as a critical mineral in the United States, which currently imports 100% of all Fluorspar consumed
domestically with >60% of all global supply sourced from China. It is essential in hydrofluoric acid production, AI
semiconductor manufacturing, advanced battery technologies, uranium enrichment, defence systems and refrigerants.
Splinter Rock Rare Earth Project – Western Australia
OD6’s 100% owned Splinter Rock Rare Earth Project in Western Australia hosts one of Australia’s largest and highest-grade
clay-hosted rare earth deposits, with a Mineral Resource Estimate of:
• Indicated: 119Mt @ 1,632ppm TREO
• Inferred: 563Mt @ 1,275ppm TREO
OD6 is advancing an innovative processing flowsheet utilising heap leaching, nanofiltration and ion exchange technologies
designed to achieved ~75% Nd & Pr overall recovery plus produce a high-quality Mixed Rare Earth Carbonate/Hydroxide
product of ~56-59% TREO with low impurity levels
Gulf Creek Copper Project – New South Wales
OD6 is also advancing the Gulf Creek Copper-Zinc VMS Project in New South Wales, a historically high-grade copper mining
district with significant exploration upside.
Recent drilling and geophysical programs have confirmed high-grade copper mineralisation and identified multiple large-
scale exploration targets along more than 10km of prospective strike.
Corporate Directory
Managing Director
Non-Executive Chairman
Non-Executive Director
Financial Controller/ Joint Company Secretary
Joint Company Secretary
Technical Advisor to the Board
Contact
OD6 Metals Ltd
ACN 654 839 602
www.od6metals.com.au
Mail to: info@od6metals.com.au
Phone: +61 8 6189 8515
Level 1, 1 Alvan Street, Subiaco, WA 6008
Mr Brett Hazelden
Mr Piers Lewis
Dr Mitch Loan
Mr Joel Ives
Mr Lewis Flynn
Dr Darren Holden
Investor Relations
Lucas Robinson
Corporate Storytime
lucas@corporatestorytime.com
Phone: +61 408 228 889
Share your feedback
Discover